2011 Oct 10
Replacement works of 110 kV circuit breaker with switch completed in 110 kV transformer substation Griskonys. New equipment for relay protection and automation, RTU, telecommunications systems were provided.
|
|
2011 Jul 18
Construction of Bitėnai switchyard at the border with Kaliningrad was a strategic site for Lithuania. The switchyard is necessary for consumers in Western Lithuania to receive electricity through the grid located in Lithuania. So far power lines at Bitena
|
|
2010 Oct 05
Replacement works of 110 kV circuit breaker with switch completed in 110 kV transformer substation Valkininkai. New equipment for relay protection and automation, RTU, telecommunications systems were provided.
|
|
2010 Sep 14
Transformers, switches and relay protection and automation systems were replaced in this substation.
|
|
2010 Jan 12
This substation to Lithuanian energy system is connected by three 110 kV lines. At the reconstruction all 110 kV equipment were changed by new one. New substation control room was designed, which contained protection, RTU and telecommunication equipment.
|