2011 Jul 18
Construction of Bitėnai switchyard at the border with Kaliningrad was a strategic site for Lithuania. The switchyard is necessary for consumers in Western Lithuania to receive electricity through the grid located in Lithuania. So far power lines at Bitena
|
|
2011 Mar 16
Reconstruction of 35/10 kV part in 110/35/10 kV substation N.Akmene. All old equipment was changed by new one, 7 new substations were integrated in SCADA system.
|
|
2011 Feb 22
Purpose of this construction was to connect new user to the grid.
|
|
2011 Feb 15
Purpose of this 110/20 kV substation was to connect wind farm to the grid.
|
|
2011 Jan 26
TR46-5 is transformer substation of Lithuanian railways located in Siauliai. Project task was to reconstruct this substation changing all 10kV cubicles, installing new RTU system and transmit all data to existing SCADA system;
|